New Facility Blog: 03/04/17
Power down! The breakers for the main electrical switchgears were installed for all four mains ...
New Facility Blog: 02/24/17
Slow week again... Most of the activity was directed at ordering parts, and waiting on ...
New Facility Blog: 02/17/17
The activities ramped up the week, as we had hoped! The frames for the solar ...
New Facility Blog: 02/11/17
Slow week this time around, hampered in part by bad weather. The installation of the ...
New Facility Blog: 02/04/17
This was a very busy week with the solar team working hard and making excellent ...
New Facility Blog: 01/27/17
We're back! Granted, it has taken far longer than expected, but better late than never. ...
New Facility Blog: 05/14/16
Loose ends are still being tied up, but construction has wound down as we approach ...
New Facility Blog: 05/06/16
This has been a week dedicated to tying up loose ends, including electrical, mechanical, and painting. The ...
New Facility Blog: 04/30/16
We reached some important milestones this week... We passed our final plumbing inspection, as well ...